EstatePass
ca-law-businessInsurance & Liensmedium

A subcontract requires both workers' compensation and general liability. Which documentation set is most complete before mobilization?

Correct Answer

B) Current evidence of both workers' compensation and general liability coverage.

If both coverages are required, the prime should collect current evidence of both before mobilization.

Answer Options
A
Only a preliminary notice.
B
Current evidence of both workers' compensation and general liability coverage.
C
Only an unconditional final release.
D
Accept the certificate in the bid file without confirming current policy dates and required coverage.

Why This Is the Correct Answer

If both coverages are required, the prime should collect current evidence of both before mobilization.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.