A cost code has a $50,000 budget and $54,800 actual cost. What is the variance?

Correct Answer

B) $4,800 over budget.

Actual cost exceeds budget by $4,800, so the variance is $4,800 over budget.

Answer Options
A
$4,800 under budget.
B
$4,800 over budget.
C
$50,000 over budget.
D
$104,800 total budget.

Why This Is the Correct Answer

Actual cost exceeds budget by $4,800, so the variance is $4,800 over budget.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.