A labor budget is $31,500 and actual labor cost is $34,250. What variance should be reported?

Correct Answer

B) $2,750 unfavorable.

Actual labor exceeds budget by $2,750, so the variance is unfavorable.

Answer Options
A
$2,750 favorable.
B
$2,750 unfavorable.
C
$3,250 favorable.
D
$3,250 unfavorable.

Why This Is the Correct Answer

Actual labor exceeds budget by $2,750, so the variance is unfavorable.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.