A contractor shows profit on the income statement but cannot pay suppliers on time. What should be reviewed first?

Correct Answer

A) Cash flow.

Profit and cash are different; slow collections or timing gaps can create cash shortages despite profit.

Answer Options
A
Cash flow.
B
Cost-to-complete.
C
Internal control separation.
D
Receivables aging.

Why This Is the Correct Answer

Profit and cash are different; slow collections or timing gaps can create cash shortages despite profit.

Was this explanation helpful?

More ca-law-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.