In the window replacement file, a pallet weighs 960 pounds and 18 boxes weighing 42 pounds each are added. What total weight is being moved?
Correct Answer
D) 1,716 pounds.
The added box weight is 18 x 42 = 756 pounds. Adding the pallet gives 1,716 pounds.
Why This Is the Correct Answer
The added box weight is 18 x 42 = 756 pounds. Adding the pallet gives 1,716 pounds.
Why the Other Options Are Wrong
Option A: 1,596 pounds.
1,596 pounds. is below the supported result for material handling calculation; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 1,646 pounds total.
1,646 pounds total. is below the supported result for material handling calculation; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 1,676 pounds total.
1,676 pounds total. is below the supported result for material handling calculation; it likely omits allowance, conversion, coverage, or final round-up.
Memory Technique
Material Handling cart for Checking Forklift: added first, box second, whole units last.
Reference Hint
Study anchor (closed-book): memorize Material handling calculation from Cal/OSHA Title 8 Construction Safety Orders; CSLB B General Building. / Cal/OSHA Title 8 material handling load planning; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?