A 14-worker crew works outdoors for 8 hours. At one quart per worker per hour, how many quarts of water are needed?
Correct Answer
D) 112 quarts.
Fourteen workers for eight hours need 14 x 8 = 112 quarts.
Why This Is the Correct Answer
Fourteen workers for eight hours need 14 x 8 = 112 quarts.
Why the Other Options Are Wrong
Option A: 56.0 quarts.
56.0 quarts. is below the supported result for heat illness prevention; it likely drops a required step.
Option B: 84.0 quarts.
84.0 quarts. is below the supported result for heat illness prevention; it likely drops a required step.
Option C: 96.0 quarts.
96.0 quarts. is below the supported result for heat illness prevention; it likely drops a required step.
Memory Technique
If Planning Water can still reach the worker, the control is decoration.
Reference Hint
Study anchor (closed-book): memorize Heat illness prevention from Cal/OSHA Title 8 Section 3395 heat illness prevention; CSLB B General. / Cal/OSHA Title 8 Section 3395 water provision; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?