A contractor discovers termite-damaged framing behind plaster after demolition. What should be documented before extra repair work proceeds when time allows?

Correct Answer

D) Written authorization.

Changed scope should be documented with written authorization so cost, time, and responsibility are controlled.

Answer Options
A
Change directive.
B
As-built note.
C
Quality-control check.
D
Written authorization.

Why This Is the Correct Answer

Changed scope should be documented with written authorization so cost, time, and responsibility are controlled.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.