Class B TradePlanning & Estimatingmedium14% of exam part

A construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed. What is the likely schedule issue?

Correct Answer

D) Finish work is too early.

Finish installation should follow required rough corrections, inspections, and close-in work; otherwise rework and delays are likely.

Answer Options
A
Carry the estimate unchanged where a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed, and sort out the scope effect after award.
B
Use the old drawing or assumption even though the a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed item may affect labor, materials, or sequencing.
C
Use the old drawing or assumption where a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed, even though labor, material, or sequencing may change.
D
Finish work is too early.

Why This Is the Correct Answer

Finish installation should follow required rough corrections, inspections, and close-in work; otherwise rework and delays are likely.

Why the Other Options Are Wrong

Option A: Carry the estimate unchanged where a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed, and sort out the scope effect after award.

Carry the estimate unchanged where a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed, and sort out the scope effect after award. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for construction sequencing.

Option B: Use the old drawing or assumption even though the a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed item may affect labor, materials, or sequencing.

Use the old drawing or assumption even though the a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed item may affect labor, materials, or sequencing. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for construction sequencing.

Option C: Use the old drawing or assumption where a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed, even though labor, material, or sequencing may change.

Use the old drawing or assumption where a construction sequence shows cabinets installed before rough plumbing corrections are inspected and walls closed, even though labor, material, or sequencing may change. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for construction sequencing.

Memory Technique

Construction Sequencing clock for Reviewing Remodel: party, date, proof, then rights.

Reference Hint

Study anchor (closed-book): memorize Construction sequencing from CSLB B General Building Study Guide; California Building Code, Title. / CSLB B General Building Study Guide project scheduling; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.