A temporary power pole is needed for construction, but no one included it in the budget. What type of estimate miss is this?

Correct Answer

D) A temporary utility cost.

Temporary power is a project support cost and should be carried in general conditions or temporary utilities.

Answer Options
A
Add alternate.
B
Subcontractor proposal.
C
Contingency line.
D
A temporary utility cost.

Why This Is the Correct Answer

Temporary power is a project support cost and should be carried in general conditions or temporary utilities.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.