The rear roof face worksheet shows a roof sheathing area is 38 feet by 24 feet. How many square feet are needed before waste?
Correct Answer
A) 912 square feet.
Roof sheathing area is length times width: 38 x 24 = 912 square feet.
Why This Is the Correct Answer
Roof sheathing area is length times width: 38 x 24 = 912 square feet.
Why the Other Options Are Wrong
Option B: 884 square feet total.
884 square feet total. is below the supported result for roof sheathing quantity calculation; it likely omits allowance, conversion, coverage, or final round-up.
Option C: 936 square feet total.
936 square feet total. is above the supported result for roof sheathing quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: 960 square feet total.
960 square feet total. is above the supported result for roof sheathing quantity calculation; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Roof Sheathing Quantity cart for Estimating Addition: area first, length second, whole feet last.
Reference Hint
Study anchor (closed-book): memorize Roof sheathing quantity calculation from California Building Code, California Code of Regulations Title 24. / Title 24 California Building Code roof sheathing quantity concepts; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
