The subfloor takeoff covers a 17-foot by 26-foot floor using 4-foot by 8-foot panels. How many panels are needed before waste?

Correct Answer

B) 14 panels.

The floor area is 442 square feet. Each panel covers 32 square feet, and 442 / 32 = 13.8125, so 14 panels are needed.

Answer Options
A
13 panels total.
B
14 panels.
C
15 panel sheets.
D
16 marked panels.

Why This Is the Correct Answer

The floor area is 442 square feet. Each panel covers 32 square feet, and 442 / 32 = 13.8125, so 14 panels are needed.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.