A rim joist area is left open where floor framing needs lateral restraint and draft separation. What should be completed?

Correct Answer

D) Rim blocking.

Rim and edge blocking help close framing cavities and provide needed restraint or support at floor edges.

Answer Options
A
Provide solid bearing.
B
Repair detail.
C
Replace or repair it.
D
Rim blocking.

Why This Is the Correct Answer

Rim and edge blocking help close framing cavities and provide needed restraint or support at floor edges.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.