A shear wall hold-down is installed but the anchor does not connect to the foundation as detailed. What path is broken?

Correct Answer

C) Overturning path.

Hold-downs must transfer overturning forces through the specified anchorage to the foundation.

Answer Options
A
Approved repair.
B
Draftstopping may be incomplete.
C
Overturning path.
D
Drainage flashing.

Why This Is the Correct Answer

Hold-downs must transfer overturning forces through the specified anchorage to the foundation.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.