Tile is planned over a cracked slab with no movement or crack isolation review. What should be addressed?
Correct Answer
B) Crack treatment.
Cracks and movement conditions should be evaluated and treated before tile is installed.
Why This Is the Correct Answer
Cracks and movement conditions should be evaluated and treated before tile is installed.
Why the Other Options Are Wrong
Option A: Proceed with the finish work where tile is planned over a cracked slab with no movement or crack isolation review, and accept the shortcut until final walkthrough.
Proceed with the finish work where tile is planned over a cracked slab with no movement or crack isolation review, and accept the shortcut until final walkthrough. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for tile substrate preparation.
Option C: Treat the item as a color or trim preference where tile is planned over a cracked slab with no movement or crack isolation review, instead of stopping to repair the finish base condition.
Treat the item as a color or trim preference where tile is planned over a cracked slab with no movement or crack isolation review, instead of stopping to repair the finish base condition. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for tile substrate preparation.
Option D: Accept the installer's shortcut where tile is planned over a cracked slab with no movement or crack isolation review, without correcting the product, backing, or clearance problem.
Accept the installer's shortcut where tile is planned over a cracked slab with no movement or crack isolation review, without correcting the product, backing, or clearance problem. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for tile substrate preparation.
Memory Technique
Reviewing Floor envelope: right person, right date, right contents.
Reference Hint
Study anchor (closed-book): memorize Tile substrate preparation from CSLB B General Building Study Guide; California Building Code, Title. / CSLB B General Building Study Guide tile substrate preparation; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
