Resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits. What is missing?
Correct Answer
C) Adhesive checks.
Slab moisture and alkalinity checks should satisfy the flooring adhesive requirements before installation.
Why This Is the Correct Answer
Slab moisture and alkalinity checks should satisfy the flooring adhesive requirements before installation.
Why the Other Options Are Wrong
Option A: Proceed with the finish work where resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits, and rely on later cleanup to make the work look acceptable.
Proceed with the finish work where resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits, and rely on later cleanup to make the work look acceptable. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for flooring moisture testing.
Option B: Treat the item as a color or trim preference where resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits, instead of resolving the condition before the finish is accepted.
Treat the item as a color or trim preference where resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits, instead of resolving the condition before the finish is accepted. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for flooring moisture testing.
Option D: Accept the installer's shortcut where resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits, without verifying the required material or access condition.
Accept the installer's shortcut where resilient flooring adhesive is spread over a slab without checking the adhesive moisture and pH limits, without verifying the required material or access condition. does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for flooring moisture testing.
Memory Technique
Good work cannot rewind a missed slab trigger in Preparing Slab.
Reference Hint
Study anchor (closed-book): memorize Flooring moisture testing from CSLB B General Building Study Guide; California Building Code, Title. / CSLB B General Building Study Guide flooring moisture and adhesive requirements; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?