A backsplash has 35 outlets and each box extension takes 6 minutes. How many labor hours are needed?
Correct Answer
C) 3.5 hours.
The work time is 35 x 6 = 210 minutes. Since 60 minutes equal 1 hour, 210 / 60 = 3.5 hours.
Why This Is the Correct Answer
The work time is 35 x 6 = 210 minutes. Since 60 minutes equal 1 hour, 210 / 60 = 3.5 hours.
Why the Other Options Are Wrong
Option A: 2.5 hours.
2.5 hours. is below the supported result for electrical finish labor calculation; it likely skips a premium-pay or employer-cost component.
Option B: 3.0 hours total.
3.0 hours total. is below the supported result for electrical finish labor calculation; it likely skips a premium-pay or employer-cost component.
Option D: 4.0 hours total.
4.0 hours total. is above the supported result for electrical finish labor calculation; it likely pays the wrong premium tier or counts the same hours twice.
Memory Technique
Electrical Finish Labor ladder for Scheduling Kitchen: the controlling choice climb before dollars add up.
Reference Hint
Study anchor (closed-book): memorize Electrical finish labor calculation from California Electrical Code, California Code of Regulations Title 24. / Title 24 California Electrical Code boxes at finished surfaces; know the rule or calculation trigger without relying on exam-room lookup.
More Class B Trade Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
