EstatePass
ca-trade-bCore Tradesmedium

A finish crew wants to close walls before the rough electrical corrections are reinspected. What should be maintained?

Correct Answer

D) Inspection access.

Work awaiting inspection should remain accessible and visible until required inspection or correction signoff is accepted.

Answer Options
A
Poor compaction.
B
Rated firestop.
C
Relocate the garage return.
D
Inspection access.

Why This Is the Correct Answer

Work awaiting inspection should remain accessible and visible until required inspection or correction signoff is accepted.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.