Class B TradeCore Tradesmedium29% of exam part

The concrete pour measures 24 feet by 16 feet at 5 inches thick. About how many cubic yards are needed before waste?

Correct Answer

D) 5.93 cubic yards.

Five inches is 0.417 feet. The volume is 24 x 16 x 0.417 = 160.13 cubic feet, and 160.13 / 27 = 5.93 cubic yards.

Answer Options
A
4.74 cubic yards.
B
5.12 cubic yards total.
C
5.54 cubic yards total.
D
5.93 cubic yards.

Why This Is the Correct Answer

Five inches is 0.417 feet. The volume is 24 x 16 x 0.417 = 160.13 cubic feet, and 160.13 / 27 = 5.93 cubic yards.

Why the Other Options Are Wrong

Option A: 4.74 cubic yards.

4.74 cubic yards. is below the supported result for concrete quantity calculation; it likely omits allowance, conversion, coverage, or final round-up.

Option B: 5.12 cubic yards total.

5.12 cubic yards total. is below the supported result for concrete quantity calculation; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 5.54 cubic yards total.

5.54 cubic yards total. is below the supported result for concrete quantity calculation; it likely omits allowance, conversion, coverage, or final round-up.

Memory Technique

Concrete Quantity cart for Estimating Equipment: inches first, feet second, whole the controlling choice last.

Reference Hint

Study anchor (closed-book): memorize Concrete quantity calculation from California Building Code, California Code of Regulations Title 24. / Title 24 California Building Code concrete quantity concepts; know the rule or calculation trigger without relying on exam-room lookup.

Was this explanation helpful?

More Class B Trade Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.