A site requires 2,400 cubic yards of fill material. The borrow pit material has a swell factor of 25%. How many cubic yards must be excavated from the borrow pit?
Correct Answer
D) 1,920 cubic yards
Bank measure = Loose measure ÷ (1 + swell factor). 2,400 ÷ 1.25 = 1,920 cubic yards
Why This Is the Correct Answer
Bank measure = Loose measure ÷ (1 + swell factor). 2,400 ÷ 1.25 = 1,920 cubic yards
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Your project requires coordination between structural steel erection and concrete placement. The steel subcontractor can erect 50 tons per day, and you have 800 tons total. Concrete can be placed 2 days after steel erection begins in each area. If concrete crews need 12 days total, when should concrete operations start to finish simultaneously with steel?
Next Question
Your subcontractor submits shop drawings for structural steel that show a connection detail different from the contract documents. What is the appropriate action?