1. A powered sewage ejector must be cleared by hand. What must occur first?

  • AReach in between automatic cycles
  • BUse the float switch as isolation
  • Isolate and control every hazardous energy source
  • DAsk a coworker to hold the switch

Why C is correct

Automatic controls can restart unexpectedly, and electrical, pneumatic, hydraulic, gravity, and stored mechanical energy may remain. Lockout, verification, blocking, and task-specific sanitation controls are needed.

2. A torch will be used near a concealed combustible cavity. What is required?

  • Use authorized hot-work controls
  • BAim water only at the pipe
  • CUse oxygen for ventilation
  • DLeave as soon as flame stops

Why A is correct

Heat can conduct into hidden material and smolder after work ends. Inspection, removal or shielding, permits, extinguishing means, ventilation, fire watch, and post-work monitoring address delayed ignition.

37 more in the bank

Answers and explanations for these are in the app.

  • A compressed-gas test is proposed at a pressure beyond the system and test-equipment rating. What should the supervisor do?
  • A heavy water heater must be moved up stairs through a narrow opening. What should the supervisor plan?
  • A ladder into a trench ends below the landing and is placed far from workers. What must be corrected?
  • A metal drain snake will be used beside damaged energized wiring in a wet area. What is the first control?
  • A plumber must enter a vault with limited access and possible sewer gas. What is required before entry?
  • A plumber plans to stand on the top cap of a stepladder while pulling heavy pipe. What is the proper response?
  • A sewer manhole tests oxygen-deficient before entry. What is the proper response?
  • A wastewater splash reaches a worker's eyes. What action is appropriate?
  • A worker is exposed to sewage through a cut during repair. Which planning approach is appropriate?
  • Before mechanized excavation for a new sewer, what is the essential first field control?
  • Before opening a line previously treated with an unknown drain chemical, what is the safest approach?
  • Demolition may disturb suspect asbestos insulation and lead-containing material. What should happen before disturbance?
  • Dry drilling concrete for pipe anchors creates visible dust. What control should be used?
  • Excavated soil and materials are piled at the edge of an occupied trench. Why is this unsafe?
  • Old pipe insulation is damaged during remodel and may contain asbestos. What should happen?
  • Why is compressed air or gas testing more hazardous than a comparable hydrostatic test?
  • Workers will enter a plumbing trench with a potential cave-in hazard. What must occur before entry?
  • A large water heater must travel up a narrow stair. What rated handling plan should the supervisor establish?
  • A line was treated with an unknown drain chemical before the plumber arrived. What should be identified before it is opened?
  • A metal drain machine will be operated in standing water beside damaged live wiring. Which hazard must be controlled first?
  • A plumber with an open cut is assigned to a sewage backup. Which exposure, hygiene, and medical-response controls belong in the plan?
  • A pneumatic test exceeds the lowest-rated fitting and gauge assembly. What should the supervisor change?
  • A short stepladder forces a worker to stand on its top while handling pipe. What access change is required?
  • A trench ladder ends below the landing and is remote from the crew. Which access defects must be corrected?
  • A valve vault has restricted access and possible hydrogen sulfide. Which entry evaluation and controls are required?
  • A worker will reach into a powered sewage ejector to clear debris. What must happen before contact?
  • Atmospheric testing finds oxygen deficiency in a sewer manhole. May entry proceed without a permit-space program?
  • Brazing is planned next to a concealed combustible cavity. Which authorized hot-work controls are required?
  • Damaged legacy pipe insulation may contain asbestos. What should occur before anyone disturbs it further?
  • Demolition exposes suspect asbestos wrap and old lead-bearing coating. What must occur before removal continues?
  • Dry core drilling for piping produces visible concrete dust. Which exposure-control method is required?
  • Employees will enter a trench with unstable soil and no protective system. What must a competent person provide before entry?
  • Spoil and pipe bundles are stacked against the lip of an occupied trench. Which hazards do they add?
  • The sewer alignment is marked, but buried utilities have not been located through the required process. What must precede excavation?
  • Torch work will heat concealed wood behind a pipe chase. Which permit, shielding, and fire-watch controls apply?
  • Wastewater splashes directly into a worker's eyes. Which immediate decontamination and reporting action is appropriate?
  • Why does a pneumatic piping test present more stored-energy risk than a hydrostatic test at similar pressure?

Practice all 40 Safety questions

Plus timed mock exams and a wrong book that follows you between the web and the app.

Start studying free

Other California C-36 content areas