A powered sewage ejector must be cleared by hand. What must occur first?

California C-36 exam practice question · Safety

A powered sewage ejector must be cleared by hand. What must occur first?

  • AReach in between automatic cycles
  • BUse the float switch as isolation
  • Isolate and control every hazardous energy source
  • DAsk a coworker to hold the switch

Why C is correct

Automatic controls can restart unexpectedly, and electrical, pneumatic, hydraulic, gravity, and stored mechanical energy may remain. Lockout, verification, blocking, and task-specific sanitation controls are needed.