A subcontractor provides a certificate of insurance. What should the prime contractor understand?

California C-20 exam practice question · Insurance & Liens

A subcontractor provides a certificate of insurance. What should the prime contractor understand?

  • AIt guarantees every claim will be paid
  • Verify the policy, limits, and exclusions
  • CIt replaces the subcontract
  • DThe certificate rewrites every policy exclusion

Why B is correct

Risk transfer depends on the actual policy and required endorsements, not the certificate alone. Contractual requirements should be reviewed before work and monitored for cancellation or expiration.

Practice 28 more Insurance & Liens questions