A healthcare facility is planning to install a generator to provide emergency power. The facility has a peak electrical load of 800kW. According to 2026 NEC Article 702.4, what is the minimum size of the generator required to meet the facility's emergency power needs?

Texas Master exam practice question · Motors & Generators

A healthcare facility is planning to install a generator to provide emergency power. The facility has a peak electrical load of 800kW. According to 2026 NEC Article 702.4, what is the minimum size of the generator required to meet the facility's emergency power needs?

  • A600kW
  • B700kW
  • C800kW
  • 900kW

Exam tip

Ensure that the emergency generator is properly sized to meet the facility's peak electrical load as specified in NEC Article 702.4.

Why D is correct

2026 NEC Article 702.4 requires that the emergency generator be sized to meet at least 100% of the facility's peak electrical load. Therefore, the minimum generator size required is 800kW, which is the correct answer.