A 200A feeder is supplying a new residential building. Which type of overcurrent protection device is required at the main service panel, according to 2026 NEC 240.21(A)?

Texas Master exam practice question · Feeders

A 200A feeder is supplying a new residential building. Which type of overcurrent protection device is required at the main service panel, according to 2026 NEC 240.21(A)?

  • ASingle-pole circuit breaker
  • Double-pole circuit breaker
  • CGround-fault circuit interrupter (GFCI)
  • DArc-fault circuit interrupter (AFCI)

Exam tip

Always check for the specific requirements for feeders to dwelling units, as they can differ from general requirements.

Why B is correct

According to 2026 NEC 240.21(A), a double-pole circuit breaker is required for feeders to a dwelling unit to prevent the possibility of a fire from spreading between the phases of a 240-volt, 3-wire, single-phase service. Single-pole circuit breakers are not sufficient for this purpose.