A residential building is being constructed with a forced-air heating and cooling system. The contractor has installed a supply duct that runs through an unconditioned attic space. Which of the following is a requirement for the duct insulation according to the 2024 International Residential Code?

ICC M1 exam practice question · Duct Systems

A residential building is being constructed with a forced-air heating and cooling system. The contractor has installed a supply duct that runs through an unconditioned attic space. Which of the following is a requirement for the duct insulation according to the 2024 International Residential Code?

  • AInsulation must be R-3 for all ducts.
  • BInsulation must be R-6 for all ducts.
  • Insulation must be R-8 for supply ducts and R-3 for return ducts.
  • DInsulation must be R-13 for all ducts.

Exam tip

Remember the specific R-values required for duct insulation in unconditioned spaces.

Why C is correct

According to Section M1503.3.1 of the 2024 IRC, supply ducts in unconditioned spaces must have insulation with a minimum R-value of R-8, while return ducts must have a minimum R-value of R-3.