EstatePass
Business & FinanceOperationsmedium10% of exam part

Your project schedule shows that Activity X can start as early as day 15 and must finish no later than day 28. The activity duration is 8 days. What is the total float for this activity?

Correct Answer

D) 5 days

Total float = Late Finish - Early Finish = Late Finish - (Early Start + Duration) = 28 - (15 + 8) = 28 - 23 = 5 days of float.

Answer Options
A
3 days
B
13 days
C
8 days
D
5 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project completion date. Using the formula: Total Float = Late Finish - Early Finish, where Early Finish = Early Start + Duration. Given: Early Start = 15 days, Duration = 8 days, Late Finish = 28 days. Therefore: Early Finish = 15 + 8 = 23 days, and Total Float = 28 - 23 = 5 days.

Why the Other Options Are Wrong

Option A: 3 days

3 days incorrectly calculates float by subtracting duration from some other value, possibly confusing free float calculations or making arithmetic errors in the basic float formula.

Option B: 13 days

13 days appears to subtract Early Start from Late Finish (28 - 15 = 13), which ignores the activity duration entirely and doesn't represent any meaningful scheduling calculation.

Option C: 8 days

8 days simply states the activity duration, which is not the same as total float. This confuses the time required to complete the activity with the flexibility available for scheduling delays.

Memory Technique

Remember 'FLEF': Float = Late Finish - Early Finish. Think 'How much FLEX time after the job is done?' Early Finish = Early Start + Duration, then subtract from Late Finish.

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.