EstatePass
Business & FinanceOperationsmedium10% of exam part

Your concrete supplier notifies you of a 3-week delay in delivery for a foundation pour scheduled in 2 weeks. The foundation is on the critical path. What should be your first priority?

Correct Answer

C) Look for alternative concrete suppliers

Since the foundation is on the critical path and the delay exceeds the scheduled start time, finding alternative concrete suppliers should be the immediate priority to minimize project impact before considering other options.

Answer Options
A
Consider using a different foundation system
B
Reschedule other activities to accommodate the delay
C
Look for alternative concrete suppliers
D
Notify the owner of the delay immediately

Why This Is the Correct Answer

Option B is correct because when a critical path activity faces a delay that exceeds the scheduled start time, the contractor's immediate priority must be to find solutions that can maintain the original schedule. Since the foundation pour is scheduled in 2 weeks but the supplier has a 3-week delay, this creates a 1-week delay to the critical path. Finding alternative concrete suppliers is the most direct solution that could potentially eliminate or minimize the schedule impact. This proactive approach addresses the root cause of the problem before exploring other more disruptive alternatives.

Why the Other Options Are Wrong

Option A: Consider using a different foundation system

Rescheduling other activities accepts the delay without first attempting to solve the concrete supply problem. Since this is a critical path activity, rescheduling will definitely impact the project completion date, making this a less desirable first option.

Option B: Reschedule other activities to accommodate the delay

Changing the foundation system would be a major design change requiring engineering approval, owner consent, and potentially permit modifications. This is an extreme solution that should only be considered after simpler alternatives like finding new suppliers have been exhausted.

Option D: Notify the owner of the delay immediately

While notifying the owner is important and will eventually be necessary, it should not be the first priority when there are still potential solutions available. A competent contractor should first exhaust reasonable alternatives to maintain the schedule before informing the owner of delays.

Memory Technique

Think 'SOLVE before TELL' - always attempt to solve critical path delays with direct action before informing others of the problem

Reference Hint

Project Management and Scheduling sections in contractor reference materials, particularly chapters on Critical Path Method (CPM) and delay mitigation strategies

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.