EstatePass
Business & FinanceOperationsmedium10% of exam part

You are managing a commercial project and need 500 cubic yards of concrete delivered over 3 days. Your regular supplier can only provide 300 cubic yards in that timeframe. What is the most appropriate procurement strategy?

Correct Answer

C) Secure a secondary supplier for the remaining 200 cubic yards

Securing a secondary supplier ensures the project stays on schedule while meeting the full material requirement. This is a standard expediting practice that maintains quality and timeline without compromising the project scope.

Answer Options
A
Reduce the concrete requirement to 300 cubic yards
B
Use a different concrete mix that requires less volume
C
Secure a secondary supplier for the remaining 200 cubic yards
D
Delay the concrete pour by one week

Why This Is the Correct Answer

Securing a secondary supplier is the most appropriate procurement strategy because it allows the project to maintain its original schedule and scope without compromising quality. This approach demonstrates proper project management by finding a solution that meets all material requirements within the specified timeframe. Using multiple suppliers is a common and accepted practice in construction when primary suppliers cannot meet full demand, and it ensures continuity of work without delays or scope changes.

Why the Other Options Are Wrong

Option A: Reduce the concrete requirement to 300 cubic yards

Using a different concrete mix that requires less volume could compromise the structural specifications and quality requirements, and may not even be feasible depending on the engineering design requirements.

Option B: Use a different concrete mix that requires less volume

Reducing the concrete requirement to 300 cubic yards would compromise the project scope and structural integrity, as the 500 cubic yards was specified based on engineering requirements that cannot be arbitrarily reduced.

Memory Technique

Remember 'SSS' - when you have a Shortage, use a Secondary Supplier to maintain Schedule

Reference Hint

Project Management and Scheduling chapter, specifically sections on material procurement and expediting practices

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.