You are installing a guardrail system on a roof. What is the minimum height requirement for the top rail?
Correct Answer
B) 42 inches
OSHA requires guardrail systems to have a top rail height of 42 inches (plus or minus 3 inches) above the walking/working surface. This standard applies to all guardrail installations.
Why This Is the Correct Answer
OSHA Standard 29 CFR 1926.501(b)(1) specifically requires guardrail systems to have a top rail height of 42 inches (plus or minus 3 inches) above the walking/working surface. This measurement is taken from the surface where workers are standing to the top of the guardrail. The 42-inch height provides adequate protection while allowing workers to lean against or hold the rail comfortably. This standard applies universally to all guardrail installations in construction, including rooftops, scaffolds, and elevated platforms.
Why the Other Options Are Wrong
Option C: 48 inches
45 inches exceeds the maximum allowable height of 45 inches (42 + 3 inches tolerance) under OSHA standards
Option D: 45 inches
39 inches is below the OSHA minimum requirement and would not provide adequate fall protection for workers
Memory Technique
Think '42 = Answer to Everything' (reference to Hitchhiker's Guide to the Galaxy) - 42 inches is the answer to guardrail height questions
Reference Hint
OSHA Construction Standards 29 CFR 1926.501 - Fall Protection in Construction, specifically subsection (b)(1) for guardrail systems
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
You are managing a project where lead paint removal is required. Workers must use respirators, but one worker claims the respirator is uncomfortable and requests to work without it. How should you respond?
Next Question
What is the primary advantage of using Structural Insulated Panels (SIPs) in construction?