EstatePass
trade-general-buildingConcrete & MasonryMEDIUM

When placing concrete in hot weather conditions in California, the CBC requires that the concrete temperature at the time of placement not exceed what maximum temperature?

Correct Answer

A) 90°F

CBC Section 1905.12 limits concrete temperature to a maximum of 90°F at placement in hot weather conditions. This requirement prevents rapid moisture loss, thermal cracking, and ensures proper hydration. Higher temperatures can lead to reduced workability and strength development issues.

Answer Options
A
90°F
B
100°F
C
95°F
D
85°F

Why This Is the Correct Answer

CBC Section 1905.12 limits concrete temperature to 90°F at the time of placement during hot weather. Above this threshold, the rapid evaporation of mix water accelerates setting time, reduces workability, increases shrinkage cracking risk, and can compromise long-term strength development. The 90°F limit is the standard referenced in this CBC section.

Why the Other Options Are Wrong

Option B: 100°F

100°F is too high and is not the limit set in CBC Section 1905.12. Placing concrete at 100°F would risk flash setting, surface cracking, and significantly reduced ultimate compressive strength. Some specifications may permit up to 95°F in certain contexts, but 100°F exceeds acceptable limits under this code section.

Option C: 95°F

95°F is the limit referenced in a different CBC section (1906.12), not Section 1905.12. This question cites Section 1905.12, where the limit is 90°F. The 5-degree difference between the two sections can trip up candidates who know the topic but misidentify which code section applies.

Option D: 85°F

85°F is more conservative than the code requires under Section 1905.12. While lower temperatures are generally better for concrete quality, the CBC does not mandate an 85°F limit for this section. This option might seem plausible as a conservative measure but is not the correct regulatory answer.

Memory Technique

For Section 1905.12: think '1905 = earlier section = lower temperature = 90°F.' The earlier the section number, the lower the temperature limit. This paired association helps distinguish the two sections.

Was this explanation helpful?

More trade-general-building Questions

When installing engineered lumber joists (I-joists) in California residential construction, what is the primary code requirement for web stiffeners?

What is the required attic ventilation ratio when a vapor retarder is installed on the warm-in-winter side of the ceiling according to the California Residential Code?

In California's Wildland-Urban Interface (WUI) areas, which underlayment requirement applies to Class A fire-rated roof assemblies?

In California, when installing a tankless water heater in a seismic zone, what additional requirement must be met beyond standard installation practices?

According to the California Building Code (CBC), what is the minimum lap splice length for #4 rebar in a concrete foundation wall in normal weight concrete with f'c = 3000 psi?

According to CBC requirements for retaining walls in California, what additional design consideration must be addressed for retaining walls over 4 feet in height located in seismic design categories D, E, and F?

When constructing retaining walls in California that exceed 4 feet in height, which CBC requirement must be met regarding drainage?

Under California regulations, when is a reduced pressure principle (RPP) backflow prevention assembly required for a residential water service connection?

Under California Title 24, what is the minimum electrical service size required for new single-family residential construction?

According to the California Building Code, buildings located in Seismic Design Category D must comply with which specific seismic design requirements?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.