When placing concrete in hot weather conditions (above 90°F), which measure is MOST critical to prevent premature setting and cracking?
Correct Answer
D) Keeping concrete temperature below 90°F and maintaining adequate moisture
In hot weather concreting, controlling concrete temperature and preventing rapid moisture loss are critical. This includes using chilled water, shading, windbreaks, and continuous curing to prevent plastic shrinkage cracking and ensure proper hydration.
Why This Is the Correct Answer
In hot weather concreting, controlling concrete temperature and preventing rapid moisture loss are critical. This includes using chilled water, shading, windbreaks, and continuous curing to prevent plastic shrinkage cracking and ensure proper hydration.
More NASCLA Questions
How long should daily reports and project correspondence typically be retained after project completion?
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
On an electrical plan, a rectangle with three parallel lines inside typically represents:
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A mechanical room contains a 480V electrical panel. According to code requirements, what is the minimum working space required in front of the panel?
Next Question
A unit price contract specifies $85 per cubic yard for concrete work. The original estimate was 1,200 cubic yards, but actual quantities used were 1,450 cubic yards. What is the total payment for concrete work?