EstatePass
Contract AdminContractseasy40% of exam part

When is the final release of retainage typically made to the contractor?

Correct Answer

C) After final completion and acceptance

Retainage is typically held until final completion and acceptance of all work, including correction of any punch list items. This ensures the owner has security for any remaining work or warranty issues.

Answer Options
A
30 days after substantial completion
B
Upon receipt of Certificate of Occupancy
C
After final completion and acceptance
D
At substantial completion

Why This Is the Correct Answer

Final release of retainage occurs after final completion and acceptance because this is when all work is truly finished, including punch list corrections and any warranty issues. The owner needs security until the project is completely done and accepted, not just substantially complete. Retainage serves as the owner's protection to ensure the contractor completes all remaining work and addresses any defects before final payment.

Why the Other Options Are Wrong

Option A: 30 days after substantial completion

Substantial completion means the project is functional but may still have punch list items or minor work remaining. Releasing retainage at this point would eliminate the owner's leverage to ensure completion of remaining work.

Option B: Upon receipt of Certificate of Occupancy

This arbitrary 30-day timeframe has no basis in standard construction practice or Florida law. Retainage release is tied to completion of work, not calendar dates after substantial completion.

Option D: At substantial completion

While a Certificate of Occupancy is important, it doesn't guarantee all contract work is complete. There may still be punch list items, landscaping, or other work remaining that needs to be finished before final payment.

Memory Technique

Think 'FINAL retainage for FINAL completion' - both words match, making it easy to remember that final release comes with final completion and acceptance.

Reference Hint

Florida Building Code Chapter 1, Section 107 - Inspections and approvals; Construction contract law references in Florida Statutes Chapter 713

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.