EstatePass
Contract AdminPermitsmedium20% of exam part

A contractor discovers that a project site contains wetlands that were not identified in the initial survey. What is the most appropriate first step?

Correct Answer

C) Immediately contact the Florida Department of Environmental Protection

When wetlands are discovered, the contractor must immediately contact the Florida DEP to determine permit requirements and avoid violations of environmental regulations. Construction should stop until proper approvals are obtained.

Answer Options
A
File for a variance with the local building department
B
Relocate the wetlands to another area of the property
C
Immediately contact the Florida Department of Environmental Protection
D
Continue construction and address the issue later

Why This Is the Correct Answer

Option B is correct because wetlands are protected under both federal and state environmental laws, and the Florida Department of Environmental Protection (DEP) is the state agency responsible for wetland regulation and permitting. When wetlands are discovered unexpectedly, immediate contact with DEP is required to assess the situation, determine what permits may be needed, and establish proper procedures to avoid environmental violations. Continuing construction without proper authorization could result in severe penalties, fines, and legal consequences.

Why the Other Options Are Wrong

Option B: Relocate the wetlands to another area of the property

Option C is wrong because wetlands cannot simply be relocated by a contractor. Wetland mitigation, restoration, or relocation requires extensive environmental studies, specialized expertise, and specific permits from regulatory agencies. This is not something a general contractor can undertake independently.

Option D: Continue construction and address the issue later

Option D is wrong because wetland issues are environmental matters regulated by state and federal agencies, not local building departments. A building variance addresses zoning or building code issues, not environmental protection requirements. The local building department does not have authority over wetland regulations.

Memory Technique

Think 'Wet = DEP' - whenever you encounter unexpected WETlands, contact DEP immediately. Environmental protection always comes before construction progress.

Reference Hint

Florida Building Code, Chapter 1, Administration section on environmental compliance, and Florida Statutes Chapter 373 regarding water resources and wetland protection

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.