When establishing site layout using batter boards, what is the primary purpose of the batter board system?

Correct Answer

B) To establish and maintain building corner locations and elevations during excavation

Batter boards are temporary wooden frames set up at building corners to hold strings that mark the exact location of foundation walls and footings. They allow the building layout to be re-established after excavation disturbs the original stakes.

Answer Options
A
To create a safety barrier around excavated areas
B
To establish and maintain building corner locations and elevations during excavation
C
To provide temporary electrical service to the construction site
D
To support concrete forms during the pour

Why This Is the Correct Answer

Batter boards are specifically designed to establish and maintain precise building corner locations and elevations throughout the construction process. They consist of horizontal boards attached to stakes placed beyond the excavation area, with strings stretched between them to mark foundation walls and footings. This system allows contractors to accurately re-establish building layout after excavation work disturbs the original survey stakes. The batter boards serve as permanent reference points that remain undisturbed during earthwork operations.

Why the Other Options Are Wrong

Option C: To provide temporary electrical service to the construction site

Safety barriers around excavations are typically orange safety fencing, barricades, or guardrails. Batter boards are layout tools positioned outside the excavation area and would not provide adequate safety protection for workers or the public.

Option D: To support concrete forms during the pour

Batter boards have nothing to do with electrical service - they are purely for surveying and layout purposes. Temporary electrical service involves setting up power panels, outlets, and electrical connections for construction equipment and tools.

Memory Technique

Think 'BATTER = Building Alignment Through Temporary External References' - the boards are external reference points that maintain building alignment during construction phases.

Reference Hint

Look up site layout and surveying sections in construction management or building construction fundamentals chapters, typically found under 'Site Preparation' or 'Foundation Layout' topics.

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.