When a change order increases the original home improvement contract price, California law requires the change order to include which element?
Correct Answer
B) The total new contract price in writing, signed by the owner
B&P Code 7159 requires that any change order increasing the contract price must be in writing and include the total new contract price, signed by the property owner. This protects consumers from unauthorized cost increases and ensures transparency in contract modifications during home improvement projects.
Why This Is the Correct Answer
B&P Code 7159 requires that any change order increasing the contract price must be in writing and include the total new contract price, signed by the property owner. This protects consumers from unauthorized cost increases and ensures transparency in contract modifications during home improvement projects.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
What is the minimum contractor license bond amount required for a California B-General Building Contractor under Business and Professions Code Section 7071.6?
Next Question
A California contractor is calculating overhead costs for bid preparation. According to standard cost accounting practices, which of the following should be classified as indirect overhead rather than direct job costs?