EstatePass
Contract AdminPermitsmedium20% of exam part

What is the typical validity period for a building permit in Florida before it expires if construction has not commenced?

Correct Answer

D) 18 months

Building permits in Florida typically expire after 18 months if construction has not commenced. However, this can vary by jurisdiction, so contractors should verify local requirements.

Answer Options
A
6 months
B
24 months
C
12 months
D
18 months

Why This Is the Correct Answer

Under Florida Building Code and typical municipal ordinances, building permits have a standard validity period of 18 months from the date of issuance if construction work has not commenced. This timeframe provides a reasonable balance between allowing permit holders adequate time to begin construction while preventing indefinite permit validity. The 18-month period is established to ensure that permits reflect current building codes and safety standards, as codes may be updated over time.

Why the Other Options Are Wrong

Option A: 6 months

6 months is too short a validity period and would not provide adequate time for contractors to secure financing, finalize plans, and mobilize for construction start.

Option B: 24 months

12 months is shorter than the standard Florida requirement and would not align with typical municipal permit validity periods in the state.

Option C: 12 months

24 months exceeds the standard validity period and would be too long, potentially allowing permits to remain valid under outdated code requirements.

Memory Technique

Think '18 months = 1.5 years' - enough time to get through a full construction season plus planning time, but not so long that codes become outdated.

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, Section 105 (Permits) or local building department permit procedures manual

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.