A residential project requires 8 inspections total. The contractor has failed 3 inspections and had to reschedule. If each re-inspection costs $75 and the original inspection fee was $50 per inspection, what is the total inspection cost?
Correct Answer
A) $625
Original inspections: 8 × $50 = $400. Failed re-inspections: 3 × $75 = $225. Total cost: $400 + $225 = $625.
Why This Is the Correct Answer
The correct answer is A ($625) because we must calculate both the original inspection costs and the additional re-inspection fees separately. All 8 inspections still require the original $50 fee regardless of pass/fail status, totaling $400. The 3 failed inspections require additional re-inspection fees of $75 each, adding $225. The total cost is $400 + $225 = $625.
Why the Other Options Are Wrong
Option C: $725
Option C ($650) overcharges by $25, possibly by incorrectly adding an extra fee or miscalculating one of the fee categories.
Option D: $650
Option D ($725) significantly overcharges by $100, likely by double-counting some fees or applying the re-inspection rate to inspections that only needed the original fee.
Memory Technique
Remember 'Original + Extra' - every inspection pays the original fee, failed inspections pay extra re-inspection fees on top of that
Reference Hint
Florida Building Code Administration chapter on inspection fees and procedures, or local jurisdiction fee schedules
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
