EstatePass
Contract AdminPermitsmedium20% of exam part

A residential project requires 8 inspections total. The contractor has failed 3 inspections and had to reschedule. If each re-inspection costs $75 and the original inspection fee was $50 per inspection, what is the total inspection cost?

Correct Answer

A) $625

Original inspections: 8 × $50 = $400. Failed re-inspections: 3 × $75 = $225. Total cost: $400 + $225 = $625.

Answer Options
A
$625
B
$575
C
$725
D
$650

Why This Is the Correct Answer

The correct answer is A ($625) because we must calculate both the original inspection costs and the additional re-inspection fees separately. All 8 inspections still require the original $50 fee regardless of pass/fail status, totaling $400. The 3 failed inspections require additional re-inspection fees of $75 each, adding $225. The total cost is $400 + $225 = $625.

Why the Other Options Are Wrong

Option C: $725

Option C ($650) overcharges by $25, possibly by incorrectly adding an extra fee or miscalculating one of the fee categories.

Option D: $650

Option D ($725) significantly overcharges by $100, likely by double-counting some fees or applying the re-inspection rate to inspections that only needed the original fee.

Memory Technique

Remember 'Original + Extra' - every inspection pays the original fee, failed inspections pay extra re-inspection fees on top of that

Reference Hint

Florida Building Code Administration chapter on inspection fees and procedures, or local jurisdiction fee schedules

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.