Using the Critical Path Method, if Activity A has an Early Start of day 5, a duration of 8 days, and the Late Finish is day 18, what is the total float for this activity?
Correct Answer
B) 5 days
Total float = Late Finish - Early Start - Duration = 18 - 5 - 8 = 5 days. This means Activity A can be delayed by up to 5 days without affecting the project completion date.
Why This Is the Correct Answer
CORRECT_ANSWER - Total float represents the amount of time an activity can be delayed without affecting the project's completion date. The formula is Total Float = Late Finish - Early Start - Duration. Substituting the given values: 18 - 5 - 8 = 5 days. This means Activity A has 5 days of scheduling flexibility before it impacts the critical path.
Why the Other Options Are Wrong
Option A: 8 days
0 days would indicate this activity is on the critical path with no scheduling flexibility, but the calculation shows 5 days of float available.
Option C: 3 days
8 days incorrectly uses just the duration value, ignoring the relationship between Early Start and Late Finish times in the float calculation.
Memory Technique
Remember 'LES-D' (Less-D): Late finish minus Early Start minus Duration = Total Float. Think 'How much LESS time Do I need?' to remember the subtraction sequence.
Reference Hint
Look up 'Critical Path Method' or 'CPM Scheduling' in project management chapters, specifically sections on float calculations and activity scheduling.
More Business & Finance Questions
A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?
What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?
A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?
When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?
A partnership agreement for a construction company should address all of the following EXCEPT:
A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?
A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?
Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?
A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?
A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?
People Also Study
Related Study Resources
Previous Question
A contractor is planning to establish a business and needs to determine working capital requirements. If monthly operating expenses are $45,000 and the average collection period for receivables is 75 days, what minimum working capital should be maintained?
Next Question
A contractor's annual payroll is $1,200,000. The FUTA rate is 6.0% on the first $7,000 of each employee's wages, and there are 25 employees. What is the maximum annual FUTA liability?
