Under OSHA requirements, when must Form 300A be posted in the workplace?

Correct Answer

C) February 1 through April 30

OSHA requires Form 300A to be posted in a conspicuous place where notices to employees are customarily posted from February 1 through April 30 of the year following the year covered by the form.

Answer Options
A
March 1 through June 30
B
December 1 through March 31
C
February 1 through April 30
D
January 1 through April 30

Why This Is the Correct Answer

OSHA Form 300A (Summary of Work-Related Injuries and Illnesses) must be posted from February 1 through April 30 of the year following the year covered by the form. This three-month posting period allows employees adequate time to review the previous year's workplace injury and illness summary. The form must be posted in a conspicuous location where employee notices are customarily displayed. This requirement ensures transparency and helps employees stay informed about workplace safety performance.

Why the Other Options Are Wrong

Option A: March 1 through June 30

December 1 through March 31 is incorrect because this timeframe begins too early (December of the same year rather than February of the following year) and ends too early (March 31 instead of April 30).

Option B: December 1 through March 31

March 1 through June 30 is incorrect because the posting period begins one month too late (March instead of February) and extends two months too long (ending in June instead of April).

Option D: January 1 through April 30

January 1 through April 30 is incorrect because the posting period does not begin until February 1, not January 1. Starting the posting period in January would be one month too early according to OSHA regulations.

Memory Technique

Think 'First Quarter Follow-up' - Form 300A is posted in the first quarter (Feb-Apr) of the year following the covered period, like a quarterly safety report review.

Reference Hint

OSHA regulations 29 CFR 1904.32 - Annual Summary requirements and posting dates

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.