EstatePass
GeorgiaGA Supplementmedium100% of exam part

Under Georgia's Right to Repair Act, how many days does a contractor have to respond to a homeowner's written notice of construction defects?

Correct Answer

D) 30 days

Georgia's Right to Repair Act requires contractors to respond in writing within 30 days of receiving notice of alleged construction defects from a homeowner.

Answer Options
A
60 days
B
45 days
C
15 days
D
30 days

Why This Is the Correct Answer

Georgia's Right to Repair Act (O.C.G.A. § 8-2-38) requires that after a homeowner serves written notice of alleged construction defects, the contractor must respond in writing within 30 days. The response must either propose a repair, offer monetary settlement, deny responsibility, or state that the claim is being investigated. This 30-day window is mandatory before the homeowner can file a lawsuit.

Why the Other Options Are Wrong

Option A: 60 days

60 days is not the response deadline under Georgia's Right to Repair Act. While 60-day periods appear elsewhere in construction law (e.g., some notice of commencement deadlines), the Right to Repair Act specifically uses a 30-day response window.

Option B: 45 days

45 days is not a timeframe specified in Georgia's Right to Repair Act. This is a distractor that falls between the incorrect 60-day and correct 30-day options.

Option C: 15 days

15 days is too short a period and does not appear in the Right to Repair Act. While 15-day periods exist in other legal contexts, the Right to Repair Act provides a full 30 days for the contractor to respond.

Memory Technique

Right to Repair = 30-day reply. Think '30 days to repair your relationship with the homeowner' — the contractor gets one month to respond and work things out before litigation begins.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.