Under Georgia law, what is the maximum time period a contractor has to file a lien claim after the last work performed?

Correct Answer

A) 90 days

Georgia law requires that a lien claim be filed within 90 days after the completion of work or the last furnishing of materials or services.

Answer Options
A
90 days
B
30 days
C
120 days
D
60 days

Why This Is the Correct Answer

Georgia's lien statute (O.C.G.A. § 44-14-361.1) requires a lien claim to be filed within 90 days after the last date labor or materials were furnished. This 90-day window runs from the last day of work or delivery, not from the contract completion date or when payment was due.

Why the Other Options Are Wrong

Option B: 30 days

30 days is far too short and does not match Georgia's statutory deadline. Some states use a 30-day window for other lien-related notices, which may cause confusion, but Georgia's lien filing deadline is 90 days.

Option C: 120 days

120 days exceeds Georgia's actual 90-day deadline. Missing the 90-day window cannot be cured by filing at 120 days — the lien right is extinguished. This option is designed to catch candidates who overestimate the deadline.

Option D: 60 days

60 days is exactly two-thirds of the correct 90-day period. This distractor is plausible enough to trap candidates who aren't certain of the exact timeframe.

Memory Technique

Think of a '90-day warranty' — in Georgia, your lien right is like a 90-day guarantee that starts the clock from your last day of work. Three months (roughly 90 days) is your window. If you wait a full season, you've lost your right.

Was this explanation helpful?

More Georgia Questions

A contractor discovers that a building permit was issued in error and the project violates setback requirements. According to Georgia regulations, what is the contractor's primary obligation?

A contractor employs workers in both construction and office roles. The construction rate is 11.2 per $100 and office rate is 0.8 per $100. Construction payroll is $85,000 and office payroll is $45,000. What is the total workers compensation premium?

Which situation would require a Georgia contractor to obtain workers' compensation insurance?

A contractor receives a stop work order from the local building official. The contractor continues working despite the order. What is the typical penalty range?

A contractor's license expires on June 30th. They submit a renewal application on July 15th. What additional requirement must they meet?

A Georgia contractor completes work valued at $15,000 on March 1st. The property owner fails to pay. What is the deadline for filing a materialman's lien?

A contractor fails to pay workers' compensation premiums and coverage lapses. An employee is injured the next day. What is the contractor's liability?

A contractor discovers that the local building official is interpreting a code provision differently than expected. What is the proper appeal process in Georgia?

A contractor's annual payroll is $450,000. If the workers compensation rate is 8.5 per $100 of payroll, what is the annual premium?

What is the threshold amount above which a contractor must be licensed in Georgia?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.