EstatePass
Business & FinanceRegulationsmedium15% of exam part

Under Florida Administrative Code 61G4, which of the following is NOT a valid reason for disciplinary action against a contractor's license?

Correct Answer

D) Charging more than the original contract amount due to change orders

Charging more than the original contract amount due to legitimate change orders is not grounds for disciplinary action, provided the change orders are properly documented and agreed upon. The other options represent violations that can result in license discipline.

Answer Options
A
Violating applicable building codes or laws
B
Abandoning a construction project without justification
C
Failing to obtain required building permits
D
Charging more than the original contract amount due to change orders

Why This Is the Correct Answer

Option C is correct because charging more than the original contract amount due to legitimate change orders is a normal and legal business practice in construction. Change orders are contractual modifications that allow for adjustments in scope, materials, or labor, and corresponding price adjustments are expected and permissible. As long as change orders are properly documented, agreed upon by both parties, and follow proper procedures, they do not constitute grounds for disciplinary action under Florida Administrative Code 61G4.

Why the Other Options Are Wrong

Option B: Abandoning a construction project without justification

Failing to obtain required building permits is a violation of construction regulations and building codes, which constitutes grounds for disciplinary action as contractors are required to ensure all necessary permits are obtained before beginning work.

Option C: Failing to obtain required building permits

Violating applicable building codes or laws is explicitly listed as grounds for disciplinary action under Florida Administrative Code 61G4, as contractors must comply with all applicable regulations and standards in their work.

Memory Technique

Think 'CHANGE is OK' - Change orders are acceptable business practice when done properly, unlike abandoning projects, skipping permits, or violating codes.

Reference Hint

Florida Administrative Code 61G4-15.006 - Grounds for disciplinary action against contractors

Was this explanation helpful?

More Business & Finance Questions

A general contractor purchases equipment worth $45,000 with a useful life of 9 years and no salvage value. Using straight-line depreciation, what is the annual depreciation expense?

What is the typical recommended coverage amount for general liability insurance for a small to medium-sized general contracting business?

A contractor estimates startup costs of $75,000 for equipment, $25,000 for initial inventory, $15,000 for insurance premiums, and $10,000 for working capital. They can finance 70% of the total. How much cash do they need?

When establishing professional relationships with architects and engineers, what is the most important factor for a general contractor to consider?

A partnership agreement for a construction company should address all of the following EXCEPT:

A contractor purchases a truck for $60,000. After 5 years, it has accumulated depreciation of $35,000. What is the truck's book value?

A contractor's business plan projects first-year revenue of $500,000 with a 15% net profit margin. If actual revenue is $450,000 with the same profit margin, what is the variance in net profit?

Using the Modified Accelerated Cost Recovery System (MACRS), construction equipment is typically depreciated over how many years?

A contractor is comparing financing options for equipment purchase. Option A: $80,000 cash purchase. Option B: $20,000 down, $65,000 financed at 6% for 4 years. What is the total cost of Option B?

A contractor purchases equipment using a capital lease with a present value of $120,000. How should this be recorded on the balance sheet?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.