Under California's Title 24 Energy Code, which of the following is required for all new residential construction to meet energy efficiency standards?
Correct Answer
B) Solar-ready construction with conduit and panel space
Title 24 Part 6 Section 110.10 requires solar-ready construction for new residential buildings, including designated solar zone areas, electrical panel capacity, and conduit pathways. This California-specific requirement supports the state's renewable energy goals and differs significantly from other states' energy codes.
Why This Is the Correct Answer
Title 24 Part 6 Section 110.10 requires 'solar-ready' construction for new low-rise residential buildings. This includes a designated solar zone on the roof, electrical panel capacity reserved for future solar, and conduit pathways from the roof to the electrical panel. This California-specific mandate supports the state's clean energy goals and was codified to make future solar installation easier and less costly.
Why the Other Options Are Wrong
Option A: Double-pane windows only
Double-pane windows alone are not the specific requirement singled out in Title 24 for all new residential construction. While energy-efficient glazing is addressed in Title 24, the code does not universally mandate only double-pane windows as a standalone requirement β prescriptive compliance involves multiple envelope and system components.
Option C: Radiant barrier roof sheathing in all climate zones
Radiant barrier roof sheathing is required in specific California climate zones (typically hot climates, such as Climate Zones 2β15) but NOT in all climate zones. Applying it universally would be incorrect β the requirement is climate-zone-dependent, making this a partial truth rather than a universal rule.
Option D: High-efficiency HVAC systems rated at 16 SEER minimum
A 16 SEER minimum for HVAC is not a blanket Title 24 requirement for all new residential construction. Title 24 sets minimum efficiency requirements for HVAC equipment, but the specific SEER threshold depends on system type, climate zone, and configuration. 16 SEER is not the universal standard cited in the code.
Memory Technique
California = Solar State. Title 24's headline residential requirement: SOLAR-READY. Think: every new California home must be 'ready to go solar' β conduit, panel space, and roof zone designated. This is California's energy signature requirement.
More trade-general-building Questions
When installing engineered lumber joists (I-joists) in California residential construction, what is the primary code requirement for web stiffeners?
What is the required attic ventilation ratio when a vapor retarder is installed on the warm-in-winter side of the ceiling according to the California Residential Code?
In California's Wildland-Urban Interface (WUI) areas, which underlayment requirement applies to Class A fire-rated roof assemblies?
In California, when installing a tankless water heater in a seismic zone, what additional requirement must be met beyond standard installation practices?
According to the California Building Code (CBC), what is the minimum lap splice length for #4 rebar in a concrete foundation wall in normal weight concrete with f'c = 3000 psi?
According to CBC requirements for retaining walls in California, what additional design consideration must be addressed for retaining walls over 4 feet in height located in seismic design categories D, E, and F?
When constructing retaining walls in California that exceed 4 feet in height, which CBC requirement must be met regarding drainage?
Under California regulations, when is a reduced pressure principle (RPP) backflow prevention assembly required for a residential water service connection?
Under California Title 24, what is the minimum electrical service size required for new single-family residential construction?
According to the California Building Code, buildings located in Seismic Design Category D must comply with which specific seismic design requirements?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In California seismic design category D2, what is the maximum height-to-width ratio allowed for wood structural panel shear walls without special detailing?
Next Question
In California's Wildland-Urban Interface (WUI) areas, what type of roof covering is required under CBC Chapter 7A?