Under California regulations, what is the maximum time period a building permit remains valid without construction activity?
Correct Answer
C) 18 months
California Building Code Section 105.5 establishes that building permits expire 180 days (6 months) after issuance if work has not commenced, but once work begins, the permit remains valid for 18 months from the date of issuance, provided work continues without interruption exceeding 180 days.
Why This Is the Correct Answer
Under California Building Code Section 105.5, building permits remain valid for 18 months from the date of issuance, provided construction work has commenced and continues without interruption exceeding 180 days. This 18-month period represents the maximum validity duration for an active building permit where work is progressing according to regulations.
Why the Other Options Are Wrong
Option A: 24 months
24 months exceeds the maximum validity period established by California Building Code. While some jurisdictions may have different timeframes, California specifically limits building permit validity to 18 months maximum when work is active and progressing.
Option B: 12 months
12 months is shorter than the actual maximum validity period. While permits do expire if work hasn't commenced within 180 days, once construction begins, the permit extends to the full 18-month maximum validity period.
Option D: 6 months
6 months (180 days) refers to the initial period before work must commence, not the maximum validity period. Once construction begins, permits remain valid for the full 18-month duration as long as work continues.
Memory Technique
Remember '18 and 6': 18 months maximum validity, 6 months (180 days) to start work and between work interruptions.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A qualifying individual for a contractor license corporation must file a bond in what amount according to California law?
Next Question
Under California Civil Code Section 8200, a contractor must serve a preliminary notice within how many days after first furnishing labor or materials to preserve mechanics lien rights?