Under California Civil Code Section 8200, a preliminary notice must be served within how many days after a claimant first furnishes labor or materials to a work of improvement?
Correct Answer
A) 20 days
California Civil Code Section 8200 requires preliminary notice to be served within 20 days after the claimant first furnishes labor, services, equipment, or materials to a work of improvement. This is commonly known as the '20-day rule' and is fundamental to preserving mechanics lien rights in California.
Why This Is the Correct Answer
Civil Code Section 8200 establishes the '20-day rule': preliminary notice must be served no later than 20 days after the claimant first furnishes labor, services, equipment, or materials to the project. Serving notice after 20 days does not extinguish lien rights entirely — it just limits the lien to work performed within the 20 days before notice was served going forward.
Why the Other Options Are Wrong
Option B: 30 days
30 days is incorrect under California law. This figure is the preliminary notice deadline in some other states. On the California contractor exam, 20 days is the correct answer whenever Civil Code Section 8200 is cited.
Option C: 10 days
10 days is too short. No standard California preliminary notice provision requires action within only 10 days. This distractor exploits candidates who underestimate the statutory period.
Option D: 60 days
60 days is far too long for a preliminary notice deadline. The 60-day figure may appear in other contexts (e.g., certain bond claim deadlines), but Civil Code Section 8200 requires action within 20 days.
Memory Technique
20 days = '2 weeks + a weekend.' Imagine the first day on the job: you have exactly two weeks plus a weekend to drop that preliminary notice in the mail. Set a calendar reminder the moment the first nail goes in.
More law-business Questions
Under B&P Code Section 7071.9, a contractor may deposit cash or securities instead of obtaining a surety bond. If a contractor chooses this option, where must the deposit be maintained and what happens to interest earned?
Under California's AB 5 law (Dynamex decision), which factor is NOT part of the ABC test for determining independent contractor status?
According to Business and Professions Code Section 7031, what is required when a licensed contractor supervises work performed by unlicensed employees on a construction project?
Under California Building Standards Code Title 24, which entity has the authority to issue building permits for most residential and commercial construction projects?
According to B&P Code 7159.5, service and repair contracts must include specific provisions. Which statement is correct regarding these contracts?
Which of the following activities is exempt from California contractor licensing requirements under Business and Professions Code Section 7048?
Under Cal/OSHA regulations in Title 8 CCR Section 5192, Safety Data Sheets (SDS) for hazardous chemicals used on construction sites must be readily accessible to employees during which hours?
Under California Business and Professions Code Section 7071.9, in lieu of a surety bond, what alternative security may a contractor provide to satisfy the contractor license bond requirement?
According to Cal/OSHA regulations, which of the following is NOT a required element of a written Injury and Illness Prevention Program (IIPP)?
A homeowner requests that a B-General Building Contractor provide a certificate of insurance naming the homeowner as an additional insured on the contractor's general liability policy. Under California law, what is the contractor's obligation?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Under California Civil Code Section 9100, what is the time limit for serving a stop payment notice on a private construction project after the claimant's last furnishing of work?
Next Question
When calculating overhead costs for bidding purposes in California, which of the following items is considered an allowable indirect cost that can be allocated across multiple projects?