EstatePass
NASCLAContractsmedium15% of exam part

Under AIA Document A201, which party has the primary responsibility for reviewing and approving shop drawings submitted by subcontractors?

Correct Answer

A) The contractor

Under A201, the contractor has the primary responsibility to review and approve shop drawings before submitting them to the architect for review.

Answer Options
A
The contractor
B
The owner
C
The architect
D
The subcontractor who prepared them

Why This Is the Correct Answer

Under A201, the contractor has the primary responsibility to review and approve shop drawings before submitting them to the architect for review.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing