Shop drawings for precast concrete panels have been submitted 3 weeks late. The critical path schedule shows this delay will impact the overall project completion. What is the most appropriate action?
Correct Answer
D) Review shop drawings normally and assess schedule impacts separately
Shop drawings must be reviewed thoroughly regardless of submission timing to ensure quality and safety. Schedule impacts should be addressed through separate channels such as schedule recovery plans or change orders.
Why This Is the Correct Answer
Option C is correct because shop drawings must always receive proper technical review to ensure structural integrity, code compliance, and safety regardless of submission timing. Quality control cannot be compromised due to schedule pressures. Schedule delays should be addressed through separate project management processes such as acceleration plans, recovery schedules, or potential change orders to maintain both quality and project timeline.
Why the Other Options Are Wrong
Option B: Reject the shop drawings due to late submission
Expediting the review process compromises thoroughness and may lead to errors being missed, potentially causing safety issues or costly rework later in the project.
Option C: Expedite the shop drawing review process
Approving shop drawings immediately without proper review is dangerous and violates professional standards, potentially leading to structural failures or code violations.
Memory Technique
Think 'Quality First, Schedule Second' - technical reviews protect lives and should never be rushed or skipped for schedule recovery.
Reference Hint
Florida Building Code Chapter 1, Administration and Enforcement sections on plan review requirements, and AIA A201 General Conditions regarding shop drawing procedures
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A construction site has a 480-volt electrical panel that needs maintenance. The electrician must follow lockout/tagout procedures. What is the minimum information that must be included on the lockout tag?
Next Question
According to the Florida Building Code, what is the minimum ceiling height required for habitable spaces in residential construction?