Shop drawings for precast concrete panels have been submitted 3 weeks late. The critical path schedule shows this delay will impact the overall project completion. What is the most appropriate action?

Correct Answer

D) Review shop drawings normally and assess schedule impacts separately

Shop drawings must be reviewed thoroughly regardless of submission timing to ensure quality and safety. Schedule impacts should be addressed through separate channels such as schedule recovery plans or change orders.

Answer Options
A
Approve shop drawings immediately to make up time
B
Reject the shop drawings due to late submission
C
Expedite the shop drawing review process
D
Review shop drawings normally and assess schedule impacts separately

Why This Is the Correct Answer

Option C is correct because shop drawings must always receive proper technical review to ensure structural integrity, code compliance, and safety regardless of submission timing. Quality control cannot be compromised due to schedule pressures. Schedule delays should be addressed through separate project management processes such as acceleration plans, recovery schedules, or potential change orders to maintain both quality and project timeline.

Why the Other Options Are Wrong

Option B: Reject the shop drawings due to late submission

Expediting the review process compromises thoroughness and may lead to errors being missed, potentially causing safety issues or costly rework later in the project.

Option C: Expedite the shop drawing review process

Approving shop drawings immediately without proper review is dangerous and violates professional standards, potentially leading to structural failures or code violations.

Memory Technique

Think 'Quality First, Schedule Second' - technical reviews protect lives and should never be rushed or skipped for schedule recovery.

Reference Hint

Florida Building Code Chapter 1, Administration and Enforcement sections on plan review requirements, and AIA A201 General Conditions regarding shop drawing procedures

Was this explanation helpful?

More Project Mgmt Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.