Material prices are subject to a 3% monthly escalation. If current steel pricing is $2,800 per ton and the project will require steel procurement in 5 months, what should be the estimated cost per ton?

Correct Answer

A) $3,245

Using compound escalation: $2,800 × (1.03)^5 = $2,800 × 1.1593 = $3,246. Rounded to nearest dollar = $3,245.

Answer Options
A
$3,245
B
$3,220
C
$3,290
D
$3,268

Why This Is the Correct Answer

Using compound escalation: $2,800 × (1.03)^5 = $2,800 × 1.1593 = $3,246. Rounded to nearest dollar = $3,245.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.