A general contractor's total project costs are $1,250,000. General overhead is 8% and profit margin is 12%. What should be the bid amount?
Correct Answer
B) $1,512,000
First add overhead: $1,250,000 × 1.08 = $1,350,000. Then add profit to the cost plus overhead: $1,350,000 × 1.12 = $1,512,000.
Why This Is the Correct Answer
Step 1 — add overhead: $1,250,000 × 1.08 = $1,350,000. Step 2 — add profit on top of the cost-plus-overhead subtotal: $1,350,000 × 1.12 = $1,512,000. Overhead and profit are applied sequentially, not both to the original base cost.
Why the Other Options Are Wrong
Option A: $1,500,000
$1,500,000 results from applying a flat 20% (8% + 12%) to the base cost: $1,250,000 × 1.20 = $1,500,000. This ignores that profit is applied after overhead, not simultaneously to the base.
Option C: $1,400,000
$1,400,000 could reflect adding only the profit (12%) to the base cost and ignoring overhead, or applying a rough 12% to $1,250,000 and rounding: $1,250,000 × 1.12 ≈ $1,400,000.
Option D: $1,456,000
$1,456,000 does not match any standard calculation path and may result from applying the percentages in the wrong order or mixing addition and multiplication steps.
Memory Technique
Cost → +Overhead → +Profit. Never combine the percentages. Think of it as a two-step escalator: ride step 1 (overhead) to a new floor, then ride step 2 (profit) from that new floor.
More NASCLA Questions
Which AIA document contains the general conditions that govern the rights and responsibilities of all parties in a construction contract?
A construction company has direct labor costs of $85,000, direct materials of $120,000, and overhead costs of $45,000 for a project. What is the total job cost?
What is the primary purpose of job cost accounting in construction?
A construction company has current assets of $350,000 and current liabilities of $280,000. What is the company's working capital?
In CSI MasterFormat, which division covers earthwork and site preparation?
In a mechanical drawing, what does 'CFM' typically measure?
In CSI MasterFormat Division 08, which of the following would typically be included?
On a mechanical plan, what does the symbol 'RTU' typically indicate?
What is the minimum preheat temperature for welding ASTM A992 steel when the ambient temperature is 15°F?
A general contractor's balance sheet shows total assets of $850,000, current liabilities of $320,000, and long-term debt of $180,000. What is the company's equity?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor's income statement shows gross profit of $1.2 million and operating expenses of $950,000. If the tax rate is 25%, what is the net income after taxes?
Next Question
Material prices are subject to a 3% monthly escalation. If current steel pricing is $2,800 per ton and the project will require steel procurement in 5 months, what should be the estimated cost per ton?
