Lead-based paint is discovered during demolition of a 1960s building. Workers will be exposed to lead levels of 35 μg/m³ over an 8-hour period. What is required?
Correct Answer
B) Respiratory protection and protective clothing
At 35 μg/m³, which exceeds the OSHA action level of 30 μg/m³ but is below the PEL of 50 μg/m³, respiratory protection and protective clothing are required along with other protective measures.
Why This Is the Correct Answer
At 35 μg/m³, the lead exposure exceeds OSHA's action level of 30 μg/m³ but remains below the Permissible Exposure Limit (PEL) of 50 μg/m³. When exposure is between the action level and PEL, OSHA requires respiratory protection and protective clothing to minimize worker exposure. This intermediate level of protection is appropriate for moderate lead exposure situations during construction activities.
Why the Other Options Are Wrong
Option A: Work area isolation and medical surveillance
Work area isolation and medical surveillance are typically required when exposure levels reach or exceed the PEL of 50 μg/m³, which is higher than the 35 μg/m³ level in this scenario.
Option D: Full containment and certified abatement contractor
Full containment and certified abatement contractors are required for much higher exposure levels or when dealing with intact lead-based paint removal, not for this intermediate exposure level during demolition.
Memory Technique
Think '30-50 Rule': Above 30 = gear up (respiratory + clothing), Above 50 = lock down (isolation + medical surveillance)
Reference Hint
OSHA Construction Standard 29 CFR 1926.62 - Lead in Construction, Table 1 for exposure levels and required protective measures
More Project Mgmt Questions
What is the minimum R-value required for wall insulation in Florida Climate Zone 2?
A subcontractor brings a new chemical product to your jobsite. Under the Globally Harmonized System (GHS), what information must be immediately available to workers?
A construction site has a trench that is 8 feet deep in Type B soil. What is the maximum allowable slope ratio for the trench walls without protective systems?
What is the maximum recommended spacing between drywall screws when attaching to wood studs?
Your crew discovers suspected asbestos-containing materials during a renovation project. What is the first action you should take?
A scaffold platform is 12 feet long and 5 feet wide. If the maximum load capacity is 25 pounds per square foot, what is the total weight capacity of this platform?
Which CSI MasterFormat Division would contain specifications for fire-stopping and firesafing materials?
In tilt-up concrete construction, what is the primary advantage of this method over conventional cast-in-place construction?
Which OSHA standard specifically addresses construction industry safety and health regulations?
A structural drawing shows a beam labeled 'W12x26'. What does the '26' represent?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
